New site footage from Wadi Zaha in Sultan Haitham City: villa and townhouse structures at 60%, earthworks complete for the mixed-use buildings, foundations under way. Then every Wadi Zaha home you can pick today.
Wadi Zaha is the first neighbourhood Al Ahly Sabbour is building in Sultan Haitham City, Muscat, and it overlooks the city’s central park. The developer’s November 2026 site update shows steady progress on both first phases. Here is what the footage shows, and what it means if you are buying from a distance.
Villas and townhouses, Phase 1 (E29)
Concrete superstructure works have reached 60%, and masonry works have commenced. From the air you can see rows of three-storey villa and townhouse structures taking shape, with concrete pumps working along the main road.
Mixed-use buildings, Phase 1 (E27)
Excavation and earthworks are 100% complete, and foundation works are ongoing. On site, crews are laying waterproofing membranes and pouring concrete for the foundations.
How we keep this information accurate
- The progress figures above are the developer’s own, taken word for word from Al Ahly Sabbour’s November 2026 construction update.
- We describe only what the site footage shows, and we do not estimate completion or handover dates.
- The site photos are stills from the developer’s footage, credited to Al Ahly Sabbour.
Why it matters if you are buying off-plan
When you buy before handover, the best evidence is what is happening on site. We follow Wadi Zaha’s construction and share each update with our clients, so you can see the progress for yourself rather than rely on a brochure.
See the homes you can choose today
Book a 20-minute video call with an Alwalaa advisor. We will walk you through the available units, the payment plans and the latest site progress, wherever you are. Message us on WhatsApp at +968 7155 5067.
Progress figures and footage: Al Ahly Sabbour construction update, November 2026.